Why we were hired: Issues with contractor adhering to contract terms and conditions
Services provided: Construction Audit and Change Order Review
While completing a close out audit of this $96M corporate campus project, we discovered that the contractor over-billed the owner $310K in costs. The over-billing was based on findings in errors on subcontractor default insurance, fee calculations, sales tax charges, and general conditions costs.
Project: Corporate Office Campus Construction
Size: $96M
Delivery Method: Design Build GMP with Lease Back
Client: Private Corporate Client
Schedule: July 2021 to December 2022